Wilgus Avenue at the North Taylor Drive intersection will be closed to through traffic beginning Monday, September 15, 2025, through mid-November 2025. This closure is necessary to accommodate infrastructure improvements associated with the intersection reconstruction.
This project will consist of storm sewer improvements, roadway improvements, new ADA compliant crosswalks at the intersection, and new traffic signals. Eastbound Wilgus Avenue will be widened to accommodate a full width right turn lane.
This project will be constructed in two (2) phases.
Phase 1 (Beginning September 15):
During Phase 2 (Beginning mid-October):
All work and traffic impacts are weather-dependent and subject to change.
The City of Sheboygan appreciates your patience and cooperation during this project. For everyone’s safety, please slow down and exercise caution in all work zones.